Excavation Commenced in August - What will happen until mid February?
Excavation of the site to a depth of approximately 9-12 metres will enable construction of a two level, 400 space carpark to be built followed by the library. The excavation stage will be completed around mid February. During excavation there will be approximately 12 truck loads of material removed per hour. To minimise disruption to traffic, pedestrians and the surrounding areas, the majority of movements will be in and out of the adjoining site at 88 Archer Street, then along Archer Street.
Indicative Timeline next 12 months
|
July - August 2008
|
Establish site and erect hoardings |
|
August 2008 - February 2009
|
Piling & shoring, and bulk excavation |
|
November 2008 - May 2009
|
Concrete foundations, columns and floor slabs up to ground level |
|
February - August 2009
|
Further concrete, steel frame structure, blockwork walls and roof |
A W Edwards Site Office
A W Edwards Pty Ltd has established a site office at Level 1/29 Anderson Street, Chatswood. Enquiries to the Site Manager, Colin Danby on ph: 9419 2916 or 0448 810 628. For specific contact information click here.
Community Billboard Project
The artwork surrounding the Civic Place site is part of the Civic Place Community Billboard Project. During construction it will become a community art and information gallery. It will be a creative hub of activity that will continue to evolve throughout the construction of Civic Place. Read about the history of the site, watch the Civic Place building grow, admire artwork or get involved with an artwork. The hoardings will become the community’s canvas; in upcoming events the community will have the opportunity to paint their art on a heart, and find their place in Civic Place. In keeping with Civic Place’s philosophy of sustainability the Billboards are printed on biodegradable Bioflex vinyl.
The Anderson Street Billboard will be designed shortly once the hoardings are erected. The artwork in this area will reflect the indigenous occupation of Chatswood and the early history of the Civic Place site.
Advertising opportunities
Limited advertising is available on the Community Billboards to those who have sponsored the Civic Place Project. If you would like further information regarding sponsorship phone Eilis O’Beirne, 9777 7693. For advertising details contact Graeme Deaner, Signarama on 0425 272 888.
Turning of the Sod
On Tuesday 19 August Civic Place Patron The Hon Bob Hawke AC along with The Hon Henry Tsang, MLC, Willoughby Mayor, Cr Pat Reilly, and other dignitaries turned the first ‘official’ sod on the site at the Ferguson Lane and Anderson Avenue side of the Civic Place site. More than 230 community members and others interested in the project attended the historic ceremony to mark the commencement of construction.